Pre-Slab
***Please note: It is the owner’s/building contractor’s responsibility to provide a method of termite control in compliance with section R320, I.R.C.
The residential inspection checklist for pre-slab includes:
- Slab depth (min. 4" nominal) with min. 4" ABC (aggregate base course)underlayment, section R506.2, I.R.C.
- Steel reinforcement per plans with bottom cover, min. 3"
- Required structural holdowns and/or special anchors per approved drawings for slabs with turned-down and/or monolithic footings
- Turned-down footings, min. (2) #4s horizontal, section R403.1.3.2, I.R.C., City amended
- Size / depth / location of interior footings per plan. Note: No piping allowed within interior footings, unless engineered
- Piping passing through concrete slab to have protective wrapping from lime and corrosives, and to allow for expansion /contraction, section P2603.3, I.R.C.
- Shearwall holdowns with minimum concrete spalling. ***Please note: Manufacturer's required location from corners to prevent concrete spalling
- Expansion and control joint locations per plan
- Listed underground nonmetallic (PVC) conduit (example: floor outlets, kitchen islands, etc.)
- Concrete-encased electrode (UFER). Example: A minimum #4 rebar, at least 20 feet in length, and having minimum concrete encasement in compliance with section E3508.1.2, I.R.C.